新闻资讯

新闻资讯

current position: Home > News Center > Industry information

contact us

Jiangsu Qinmo Ocean Engineering Co., Ltd.

CONTACT:+86 517 83711299

E-MAIL:master@qm-marine.com

WEBSITE:www.qm-marine.com

ADRESS:28 Shenzhen East Road, Qingjiangpu District, Huai 'an City, Jiangsu Province

Installation and commissioning steps of Marine crane

2024-01-19 11:28:04
times

The installation and commissioning of Marine crane is an important step to ensure the normal operation and the expected performance of the equipment. The following are the general steps for the installation and commissioning of Marine cranes:

Installation steps:

Preparation work:

Plan and prepare carefully before installation, including obtaining relevant equipment and tools in advance.

Inspect the installation site to ensure that it meets safety and operational requirements.

Equip the required labor and operators and ensure that they have received relevant training.

Equipment unloading and assembly:

Unload the various components of the Marine crane from the transport vehicle.

Assemble the main components of the crane, including boom, boom, hook, control system, etc., according to assembly drawings and instructions provided by the manufacturer.

Foundation installation:

Install the base of the equipment on the hull according to the design requirements. Ensure that the foundation is firmly fixed and meets the requirements of safety and stability.

Equipment installation:

Install the assembled crane parts onto the base. Use bolts and fasteners to connect the parts together and make sure the connections are strong.

crane

Electrical connection:

Make electrical connections, including power lines, control lines, sensors, etc.

Check cables and connectors to make sure they are in good condition.

Hydraulic system installation:

Install hydraulic systems, including hydraulic pumps, valves, fuel tanks, etc. Make sure the hydraulic line is connected correctly and there are no leaks.

Safety equipment installation:

Install safety equipment, such as anti-collision system, emergency stop button, limit switch, etc.

Debugging steps:

System check:

Complete system inspection to ensure all electrical and hydraulic systems are operating properly.

Check the working status of each sensor to ensure that they can accurately sense the state of the device.

Electrical system commissioning:

Start the electrical system and check the working status of the control panel and electrical components.

Verify the individual buttons and switches in the remote control or operating panel to ensure that they match the action of the device.

Hydraulic system commissioning:

Start the hydraulic system to ensure the normal operation of the hydraulic pump and the hydraulic oil pressure within the normal range.

Check and adjust the hydraulic valves through the control system to ensure that all parts of the hydraulic system are working properly.

Mechanical system commissioning:

Start the mechanical system and check the running status of the gear, bearing, transmission and other mechanical components.

Make sure the lubrication system of mechanical parts works properly and fill lubricating oil.

Lifting test:

Carry out no-load lifting test to verify the hook, boom, telescopic function of the crane.

Adjust the lifting speed, turning speed and lifting speed to ensure that the parameters meet the design requirements.

Safety equipment testing:

Test the work of safety equipment, including the detection of anti-collision systems and the effectiveness of emergency stop buttons.

Final verification and adjustment:

Perform final equipment validation to ensure all systems are working in harmony.

Make final adjustments to the system to meet the actual operation requirements.

During the whole installation and commissioning process, the operation manual and safety procedures provided by the crane manufacturer are strictly followed to ensure that the installation and commissioning process is safe and controllable. After installation and commissioning, you need to perform equipment acceptance and performance tests to ensure that the equipment can be put into use safely and reliably.

Recently Viewed:

news.related_news

  • Menu

Jiangsu Qinmo Ocean Engineering Co., Ltd.

CONTACT:+86 517 83711299

E-MAIL:master@qm-marine.com

ADRESS:28 Shenzhen East Road, Qingjiangpu District, Huai 'an City, Jiangsu Province


微信咨询 打开抖音扫一扫